Home › Guides › Retaining Wall Regulations NZ: Consent Rules Explained

Retaining Wall Regulations NZ: Consent Rules Explained

When a retaining wall needs a building consent in NZ, what counts as surcharge, when a resource consent applies, and how the Wellington councils fit in.

In short

  • Exempt from building consent: 1.5 m or less of retained ground AND no surcharge.
  • A driveway, building, pool, second wall or rising slope above the wall is surcharge.
  • Resource consent is a separate question answered by your council's district plan.
  • A barrier is needed where someone could fall 1 m or more.

Two sets of rules apply to a retaining wall in New Zealand. The Building Act decides whether you need a building consent, and it is the same nationwide. The district plan decides whether you need a resource consent, and it changes from one council to the next. This guide explains both in plain terms. It is general information, so confirm the position for your property with your council.

The building consent exemption

Schedule 1 of the Building Act 2004 lists building work that can be done without a consent. For retaining walls the exemption has two conditions, and both must be met.

  1. The wall retains no more than 1.5 metres depth of ground.
  2. The wall does not support any surcharge or any load additional to the load of that ground.

If the wall is 1.6 metres, it needs a consent. If it is 900 mm but holds up a driveway, it needs a consent. People remember the first condition and forget the second.

What counts as surcharge

  • A driveway, parking pad or any area vehicles use near the top of the wall.
  • A building or part of one, including a garage, sleepout or deck foundation.
  • A swimming pool or a large water tank.
  • Another retaining wall above and close behind.
  • Ground that slopes upward behind the wall instead of running level.

The last item matters most on hill sections. A wall cut into a Wellington hillside nearly always has rising ground behind it. Whether that slope is steep enough and close enough to count is an engineering judgement, so ask before assuming a hillside wall is exempt.

Terraced walls

Two 1.2 metre walls stepped up a bank are not automatically two exempt walls. If the upper wall sits within the zone of soil the lower wall is holding, it loads the lower one and the pair behave as a single tall wall. A common rule of thumb is to set the upper wall back by at least the height of the lower wall. Treat that as a starting point and have an engineer confirm it.

Exempt does not mean unregulated

An exempt wall must still comply with the Building Code: it has to be stable, durable and safely drained. If it fails and damages a neighbour's property, the fact that no consent was needed is no defence. Many owners choose to have a low wall engineered anyway when it sits on a boundary or near a house.

The rural exemption

A second Schedule 1 exemption allows a retaining wall up to 3 metres in a rural zone without consent, provided a chartered professional engineer has designed or reviewed it and the wall is at least its own height away from any legal boundary or existing building. Around Wellington this can apply in places like Mākara, Ōhāriu, Whitemans Valley, Akatarawa and rural Kāpiti. The council can confirm the zoning.

Barriers on top

Where a person could fall 1 metre or more from the top of a wall, Building Code clause F4 calls for a barrier. On a house section that normally means a fence or balustrade at least 1 metre high that a small child cannot easily climb or slip through. The barrier adds load to the wall, particularly in wind, so it should be allowed for in the design.

When a consent is needed

You will need an engineer to design the wall and provide a producer statement (PS1). The application goes to the council with drawings, calculations and sometimes a geotechnical report. During the build the council or the engineer inspects key stages such as post holes, footings and steel, and the engineer usually issues a PS4 at the end. The council then issues a code compliance certificate. Allow $2,000 to $5,000 for the engineering and $2,500 to $6,500 for consent fees and council charges, plus several weeks for processing.

Resource consent and district plans

District plans control things the Building Act does not: how high a structure can be near a boundary, how much earth can be moved and how deep a cut can be, what happens near streams, the coast, ridgelines, protected trees and heritage buildings, and what can be built in hazard areas. A retaining wall can trigger any of these. The thresholds differ between councils and change when plans are reviewed, so this guide does not quote them.

In the Wellington region the authority depends on where the property is:

  • Wellington City Council for the city and its suburbs, including Tawa and Mākara.
  • Hutt City Council for Lower Hutt, Petone, Wainuiomata and Eastbourne.
  • Upper Hutt City Council.
  • Porirua City Council.
  • Kāpiti Coast District Council.

Greater Wellington Regional Council has its own rules for work in or beside streams and for larger earthworks. Each city or district council has a duty planner who can tell you whether a proposal needs resource consent. Ring before the design is fixed.

Road reserve and encroachments

On many hillside streets the legal road is wider than the sealed carriageway and footpath. A front wall, a parking pad or a set of steps can sit on that strip of council land. Wellington City Council manages this through road encroachment licences. Before rebuilding a wall at the street edge, ask the council whose wall it is and what approval it needs.

Pipes and boundaries

Building over or close to a public stormwater, wastewater or water pipe needs approval from the council or its water operator first. On boundaries, a wall and its footing should sit entirely on the land of the owner who needs it. The Fencing Act does not cover retaining walls, so sharing the cost is a matter of agreement. See replacing an existing wall for how that usually plays out, and NZS 3604 and retaining walls for the standards question.

Questions people ask

Can I build a 1.5 metre retaining wall without consent?

Only if nothing but level ground sits behind it. With a driveway, building, pool, another wall or a rising slope above, a 1.5 metre wall needs a building consent and an engineer.

Do I need consent to replace an existing retaining wall?

The same test applies as for a new wall. Replacing like with like does not create an exemption. If the wall is over 1.5 metres or carries a surcharge, the replacement needs a consent.

How is retaining wall height measured?

For the Building Act exemption, it is the depth of ground retained: the difference between the ground level at the top and at the bottom of the wall. District plans may measure height differently, so check with your council.

Does my neighbour have to agree to my retaining wall?

Not if the whole wall, its footing and its drainage are on your land and it complies with the rules. You will need their agreement to work from their side or to build on the boundary line, and it is good practice to tell them early.

Need a firm price for your own wall?

Tell us where the wall is and roughly how big. We line up a site visit, and the builder follows it with a written price broken into its parts. Or phone and talk it through.

Call 04 887 1262

Request a free quote

Tell us about the job. We reply within one working day.

Free site visit and written quote · No obligation

Call nowFree quote